The job is terminated at the end of the requested or assigned time.


Job Queues

The Padobran computer cluster contains two job queues, cpu with a maximum job duration of 7 days, and cpu_30 with a maximum job duration of 30 days. Cpu_30 has five exclusive nodes, and overlaps with the cpu queue on another six. On those six nodes, cpu_30 has a higher priority than the cpu queue.

QueueNumber of nodesNumber of cores per nodeWorking memory per node (GB)Job execution time (h)TMPDIR
cpu4512847500:00:00 - 168:00:00/beegfs-fast/scratch
cpu_3011-6 exclusive128475168:00:01 - 720:00:00/beegfs-fast/scratch

...